Production capacity (CAPA) analysis sheet

A capacity analysis answers one question per process: how many units can it make in a day and a month, and is that enough for the demand? Enter machines, hours per day, utilization and cycle time for each process and the sheet computes daily and monthly capacity, the load rate against monthly demand and the spare capacity. The bottom row takes the minimum across processes, because a line is never faster than its slowest step.

Fill it in right here

Click any blank cell and type. Totals and amounts calculate as you go, and you can print it, save it as PDF or download the filled-in Excel file.

My documents

Saved in this browser only. Save versions to keep separate customers or dates. Clearing site data removes them; download important files.

Open all my documents
Production Capacity (CAPA) Analysis
Process / equipmentMachinesHours per day (h)UtilizationCycle time (s)Daily capacity (units)Monthly capacity (units)Monthly demand (units)Load rateSpare capacityNotes
Line capacity (bottleneck process)

Daily capacity = machines × hours per day × 3,600 × utilization ÷ cycle time, rounded down; leave utilization blank for 100%. A line makes no more than its slowest process, so the bottom row takes the minimum of the capacity columns and the maximum demand. Load rate = demand ÷ capacity; above 100% means overtime, another shift or more equipment. CAPA here means capacity, not corrective action.

How to use this tool

  1. Enter the plant or line, the analysis period, the working days per month and your name in the header. Working days drive the monthly capacity column.
  2. Open the Excel file and list each process or machine group with the number of machines, hours per day, expected utilization, cycle time in seconds and the monthly demand. Capacity, load rate and spare capacity are formulas.
  3. Read the bottom row for the line capacity and its load rate, then plan overtime, extra shifts, new equipment or cycle-time improvement for the process that limits it.

Frequently asked questions

How is daily capacity calculated?

Daily capacity = machines × hours per day × 3,600 × utilization ÷ cycle time in seconds, rounded down to whole units. One machine running 8 hours at 85% utilization with a 12-second cycle makes 1 × 8 × 3,600 × 0.85 ÷ 12 = 2,040 units. Leave utilization blank to assume 100%; monthly capacity multiplies by the working days in the header.

Why does the bottom row show the minimum, not the sum?

Processes in a line work in series, so the finished output cannot exceed the capacity of the slowest process. The totals row therefore takes the minimum daily and monthly capacity and the maximum demand, and computes the load rate from those two figures: that is the real capacity of the line and the bottleneck to invest in first.

What load rate is too high?

Load rate = monthly demand ÷ monthly capacity. Above 100% the plan cannot be met without overtime, an extra shift or more equipment. Many plants treat 85 to 90% as the practical ceiling because changeovers, breakdowns and absences eat the rest; spare capacity, 1 − load rate, shows how much room is left.

Is this the same CAPA as corrective and preventive action?

No. In production planning CAPA is short for capacity, the output a process or line can deliver. In quality management CAPA means corrective and preventive action, the report that closes a nonconformance. This sheet is about capacity; the CAPA report template in this library covers the quality meaning.